Client: Confidential

Location: Avonmouth, Bristol

Remediation Value: £300,000

Project: Phased site investigation and remediation to allow development of land for commercial use. Historic demolition of a former beryllium alloy factory had resulted in waste materials being deposited in 5m deep concrete pits. The backfill deposits included process plant along with demolition waste and drums of contamination as well as bags of asbestos powder. The nature of the dangerous contaminants meant stringent Health, Safety and Environmental controls were required.