Steam Enhanced Remediation of creosote at Former Timber Treatment Facility

timber75Removal of predominantly creosote contamination from a former timber treatment facility.

 

 


Client Confidential
Location Burton-On-Trent
Value £350k

Project

Removal of predominantly creosote contamination from a former timber treatment facility.

Steam Enhanced Remediation (SER), Free Product pumping, Dual Phase Vacuum Extraction (DPVE) and Air Sparge (AS) targeting remediation of Dense Non-Aqueous Phase Liquids (DNAPL) and Semi-Volatile impacted groundwater and soils.

Challenges

The remediation objectives required the complete removal of DNAPL and betterment of contaminant concentrations in both soils and groundwater. The maximum DNAPL thickness was 700mm. During the installation phase it was evident that the plume area was larger than expected, the area increased from 600m2 to 1100m2. The flexibility of the equipment allowed the treatment area and remediation system to be redesigned accordingly.

Churngold Solution

The SER system was bespoke built, comprising steam generation & injection systems. Over forty-five wells were available for Steam injection, which could also be used for AS or DNAPL pumping. Twelve wells were available for DPVE.

High temperatures were recorded after only one week of SER, the temperature increased throughout the heating period as steam injection was intermittently pulsed in different areas of the site to target hot spot zones.

The treatment resulted in subsurface temperature increasing from an average of 90oC to 59oC. Heavily impacted areas were heated to >95oC to allow Hydro Pyrolysis Oxidation, a process where oxygen becomes a powerful chemical oxidant at temperatures greater than 90oC.

DNAPL pumps and DPVE were used to remove the mobilised Free Product. A total of over 4500kg was removed.

Current Status

The remediation was undertaken over a 7-month period removing free product from all wells. The project was also completed on programme and successfully validated over a 4 month period by a third party consultant.


 

timber1
Temperature Profile of site after 1 week of SER

 

 

 

 

timber2
Temperature Profile of site after 11 week of SER