Crick Road Care Home
Project Overview
Client: Lovell
Project Name: Crick Road Care Home
Location: Crick Road, Caldicot
Sector: Residential
Engineer: Intrado
Architect: Pentan
Project Value: £800k
Project Period: 24 weeks
Churngold Construction are contracted by Curo for the ongoing delivery of a new housing development at Century Park in Lawrence Weston, Bristol.
This residential scheme encompasses 128 homes, including 30% affordable housing for social rent and Shared Ownership. Churngold served as Principal Contractor for the initial 18 weeks of enabling works before transitioning to Curo. Churngolds initiative-taking and solution-oriented approach focuses on minimizing costs and achieving project milestones, ensuring a successful and timely delivery.
The construction process began with the stripping of topsoil. The Construction of adoptable roads, installation of mainline drainage systems, followed by services. Ground floors were built using traditional block and beam on precast piled foundations. By working in a collaborative manner with Curo Management, Curo Technical department, Craddy’s and GCP Architects the project has proven to be successful.
Key work carried out
Earthworks, topsoil removal, cut and fill exercise
Storm and Foul drainage systems. Attenuation Tanks and Hydro Brake.
Sub-structure.
Blockwork, beam & block.
Concrete floor slabs
Adoptable Highway works, car park
Paving
Hard Landscaping
New ducting and services
Topsoil placement
Churngold successfully managed
Existing Services
Environmental aspects, proximity of badger sett.
Protection of existing hedge rows