Halo & Millwrights Place
Project Overview
Client: Bruton Developments
Project Name: Halo & Millwrights Place 278 Works
Location: Bristol
Engineer: Arup
Architect: Bush
Sector: Public
Project Value: £2.9M
Project Period: 95 weeks
Public realm work, in order to complete the Client’s overall scheme to deliver a mixed-use development called Halo & Millwrights Place.
We were successful in winning this contract off the back of Early Contractor Involvement. This method of procurement mitigated huge cost and time risk for the Client. JCT 2016 Intermediate Contract, with amendments.
Key work carried out
Pavement and road realignment
Drainage
Kerbing and paving
Services including diversions and street lighting
Supply and install street lighting
New street signs
Bridge jointing
Tarmac surfacing
Landscaping – planting, trees etc
Churngold successfully managed
We were Principal Contractor
Key stakeholders including Bristol City Council, the Client, residents and businesses effected by the construction works
We obtained adoption of the works on time
Night working was required for many aspects of the works