Horizon 38 Plot B1
Filton Cubex


Project Overview

Client: MCS

Project Name: Horizon 38 Plot B1 Filton Cubex

Location: Filton, Bristol

Sector: Public

Project Value: £1.6M

Project Period: 65 weeks

The third project within a 500m radius with the repeat client MCS. A speculative build for the Developer Cubex.

Due to the site conditions at the end of the calendar year and the moisture content of the sub-soil, It was decided that cement stabilisation was required over the pile matt areas. CCL rapidly mobilised a rig from trusted sub-contractor Terrafirma whom stabillised the very soft clay under the pile matt and made the slurry that had formed into a usable material. Passes of the stabilisation rig firstly at 1% then 3% in 300mm layers ensured the design CBR readings were hit on programme for the handover of the pile matt. 

All foundations that followed were complete on programme along with the foul and storm systems. A large attenuation tank in the centre of the external area was installed early to avoid sterilising the area as other contractors joined the project.

Key work carried out

  • Cut and Fill 

  • WAC testing & WAC Map 

  • Cement Stabilisation 

  • Pile attendance

  • Pile cropping

  • Pile caps / Cores

  • Drainage

  • Water / gas proofing

  • Retaining walls

  • S278 Kerbing and paving

  • Services installation

  • Block Paving

Churngold successfully managed

  • Cut & Fill exercise with further WAC testing 

  • Stabilisation 

  • Key Milestone dates reached 

  • Working with the piling contractor 

  • Installation of large attenuation tank 