Morriston Hospital - Swansea


Project Overview

Client: Kier

Project Name: Morriston Hospital

Location: Swansea

Sector: Health

Project Value: £2.1M

Engineer/Architect: Curtin’s/IBI

Project Period: 84 weeks

The project involved the construction of a new substation to alleviate the load being drawn from the existing. Over 2kms of 11kv cabling was also installed, the trenching for this when around the perimeter of the live hospital.

The new substation will ensure there are fewer power cuts for the vital services the hospital provide along with contributing to net zero with the more efficient equipment. 

Key work carried out

  • Earthworks.

  • Attenuation Tanks & Ponds.

  • Drainage, Services.

  • Reinforced Foundations.

  • Floor Slabs, Waterproofing.

  • Car Parks & Roads.

  • 278 Works.

  • Hard Landscaping.

Churngold successfully managed

  • Multiple unknown existing services.

  • Logistics around live health centre.

  • Drainage into live highway.

Previous
Previous

Fairwater Learning Campus

Next
Next

SRU Nevill Hall Hospital