Sulis Hospital - Bath


Project Overview

Client: Integrated Health Projects

Project Name: Sulis Hospital

Location: Bath

Sector: Health

Project Value: £2.5M

Engineer/Architect: Clarkebond / Stride Treglown

Project Period: 35 weeks

Churngold Construction were contracted by Vinci to deliver the groundworks, Carparks and infrastructure for the extension to Sulis Elective Orthopedic Centre. 

Churngold’s initiative-taking and solution-oriented approach focuses on minimizing costs and achieving project milestones, ensuring a successful and timely delivery.

The construction process began by stripping off topsoil installing stone to create a staff carpark.

The main works consisted of pad foundations, drainage and kerbing works all within the Bath stone strata.

Key work carried out

  • Earthworks.

  • Importing Stone.

  • Pad Foundations.

  • Storm and Foul Water Drainage.

  • Infiltration Tanks.

  • Services Installation.

  • Retaining Walls.

  • Kerbing.