Sulis Hospital - Bath
Project Overview
Client: Integrated Health Projects
Project Name: Sulis Hospital
Location: Bath
Sector: Health
Project Value: £2.5M
Engineer/Architect: Clarkebond / Stride Treglown
Project Period: 35 weeks
Churngold Construction were contracted by Vinci to deliver the groundworks, Carparks and infrastructure for the extension to Sulis Elective Orthopedic Centre.
Churngold’s initiative-taking and solution-oriented approach focuses on minimizing costs and achieving project milestones, ensuring a successful and timely delivery.
The construction process began by stripping off topsoil installing stone to create a staff carpark.
The main works consisted of pad foundations, drainage and kerbing works all within the Bath stone strata.
Key work carried out
Earthworks.
Importing Stone.
Pad Foundations.
Storm and Foul Water Drainage.
Infiltration Tanks.
Services Installation.
Retaining Walls.
Kerbing.