Exmouth Junction
Project Overview
Client: Places for People
Project Name: Exmouth Junction
Location: Exeter
Sector: Residential
Project Value: £8.55M+
Engineer/Architect: Hydrock/Stantec/BDC/Gould Singleton Architects
Project Period: 134 weeks
Site wide remediation of this former network rail siding close to a busy main line junction. Works involved delineation of hydrocarbon and asbestos hotspots with in-situ treatment and offsite disposal. Materials Management Planning under CL:AIRE and delivery of the site works in accordance with the agreed strategy together with the management and record keeping necessary to meet the regulatory requirements.
Deployment of circular strategies (WRAP Protocol, MMP etc) to maximize re-use and value of site won materials.
Bulk earthworks utilising suitable site won materials to construct the development platform. Gas monitoring and vapor spike surveys to develop the ground gas risk assessment.
Delivery of all groundworks, drainage, infrastructure and external works to 104 housing plots and 64-unit apartment block.
Key work carried out
Site Clearance
Site Wide Remediation
Materials Management Plan (under CL:AIRE)
Earthworks
Foundations, Drainage & External Works
Churngold successfully managed
Site restrictions – busy major roads on two sides of the site.
Major Rail line on site boundary.
Shared main access with multiple other development sites.
Co-ordination with major sewer diversion works with easement through part of the site during the works.
Delivery of the Remediation, Phased Earthworks and groundworks phase.