Former Lansdowne Hospital Site
Project Overview
Client: Lovell
Project Name: Former Lansdowne Hospital Site
Location: Sanatorium Road
Project Value: £4M
Engineer / Architect: Dennis Hailyar
Project Period: 46 weeks
Following appointment by Lovell, Churngold are carrying out the civil engineering and finishing works package for the construction of 44 Houses and 3 apartment blocks at Former Lansdowne hospital.
The package includes, drainage and services installation, earthworks operations, road formation and the creation of 2 new swales to support the need to control adding additional pressure on the existing drainage systems.
Key work carried out
Churngold successfully managed
Carrying out Earthworks operations inline with Environmental constraints to ensure the safety and wellbeing of the nature and habitants within the area.
Installation of drainage and services infrastructure.
Installation of 2 large swales.
Road formations works.
Foundation works.
Finishing works to all areas.