Quidel
Project Overview
Client: Kier Construction
Project Name: Quidel
Location: Felindre Meadows, Pencoaed
Project Value: £2.5M
Engineer / Architect: C33 Consult / EDT Partnership
Project Period: 80 weeks
Following appointment by Kier Construction, Churngold are carrying out the civil engineering and infrastructure works package for the extension of Quidelortho medical technology and diagnostics company.
The package included drainage and services installation, earthworks and external service yards.
Key work carried out
Churngold Successfully managed
Installation of drainage and service infrastructure.
Installation of concrete foundations and floor slabs.
Installation of concrete services yards to support the additional mechanical plant required.
High-risk activities being delivered safely while the project remains live.
Works progressing in line with the project programme.