Wepa Infrastructure
Project Overview
Client: Wepa
Project Name: Wepa Infrastructure
Location: Bridgend
Project Value: £2.6M
Engineer / Architect: BHM
Project Period: 12 weeks
Following the appointment by BHM, Churngold carried out culvert diversion and creation of piling mat.
The package included the cutting and turning of the existing ground down to 3 meters, removal of any obstructions and then creating a piling mat, including a diversion of a 1350mm cuvert diversion and chemical line.
Key work carried out
Churngold Successfully managed
Reduce digging down to 4 meter whilst keeping existing water levels under control.
Removal of all concrete obstruction.
Diversion of both 1350mm culvert and 300mm chemical line.
Create piling mat that satisfies the client and design requirements.
Carrying out Earthworks operations in line with Environmental constraints to ensure the safety and wellbeing of the nature and habitants within the area.
High-risk activities being delivered safely while the project remains live.
Works progressing in line with the project programme.